Kitchen remodel — DEMO — DO NOT DELETE — Kitchen remodel, Frank Foster

1 Main Street Smithfield VA

Bookmark this page so you can check back on it any time — it updates as the work moves along.

Where we are

2 of 10 stages complete
Your contractor checks these off as the work gets done.

Latest update

Aug 13, 2:02 PM

Kitchen cabinets purchased. Will be delivered in 2 weeks

The plan

Permit & Project Mobilization

2-3 days

Pull building permit, install site protection, zip doors, and dust barriers throughout all work areas before any work begins.

Selective Demolition

4-6 days

Demo all cabinets, soffits, partition wall, ceramic tile, masonry board, carpet, padding, and tack strips. Remove plaster, trim, and framing at wall removal areas.

3

Rough Plumbing & Electrical Relocations

3-5 days

Relocate sink and dishwasher plumbing to new kitchen layout. Relocate electrical from removed partition wall and rough in 6 recessed lights and D/W circuit.

4

Framing Patch, Floor Patch & Underlayment

2-3 days

Patch framing at all wall removal areas. Install OSB floor patch at partition wall removal. Install proper-thickness plywood underlayment in kitchen for bamboo flooring.

5

Drywall / Plaster Board Hang & Finish

4-6 days

Hang drywall and plaster board at all demo and wall-removal areas. Apply corner beads, finish, and texture all surfaces to match existing.

6

Cabinet Installation

3-4 days

Install all base cabinets, wall cabinets, and pantry cabinets per kitchen cabinet drawing No. 1, including 2 custom pantry doors on sink side.

7

Countertops, Flooring & Trim

5-7 days

Template and install solid surface countertops. Install bamboo flooring in kitchen and family room with transitions and quarter round. Install crown molding at wall cabinets and family room.

8

Finish Plumbing, Electrical & Appliance Set

2-3 days

Set kitchen sink, faucet, and reconnect dishwasher. Install recessed lights, light fixtures, and chimney hood. Reinstall refrigerator and dishwasher.

9

Paint — Kitchen, Family Room & Hallway Blend

3-4 days

Finish paint all ceilings, walls, and trim in kitchen and family room. Computer-match and blend ceiling and accent wall in hallway at LVL assembly area.

10

Punch List, Final Clean & Closeout

1-2 days

Install cabinet hardware. Complete quarter rounds. Remove zip doors and site protection. Final clean and punch list walk-through with owner.

Earlier updates

Aug 13, 2:01 PM

Mobilization will be completed this Tuesday